How reassign the Approval process from all PWA projects? RRS feed

  • Question

  • Hi

    I am the Global Admin from PWA, and I have three teammates like Admin in Project Online. I need to assign the Task Update in the Approval Center from our PWA to one of my three colleagues.

    We change all the Timesheet Manager in the Edit Resource, and assign to my colleague, but doesn't work. The task updates came into email to me and I am the only person to have this messages.

    What I need to change or assign to do this? Also we try create another new Enterprise Project from my colleague´s account but...I am the only person to have the task updates in the Approval Center.

    Could you help me?

    Kind regards

    Alberto Cruz

    Monday, August 21, 2017 4:12 PM

Answers

  • Hi,

    You have to change Status Manager of each task in every project plan from yourself to the other person.
    Please check how to do that here http://blog.epmainc.com/how-update-status-manager-enterprise-project-when-using-project-server-2013/

    Regards,

    Mariusz

    Tuesday, August 22, 2017 9:01 AM