What are peoples recommendations for managing part time resources? RRS feed

  • Question

  • Any guidance/tips on how to best manage part time resources in PWA2013 would be greatly appreciated.
    Monday, September 14, 2015 2:51 PM

All replies

  • Hi Kev,

    I would amend the resource calendar to reflect their working hours in total, but I don't tend to reflect the actual start time - it's just too much micro management.  For example, if a user works 20 hours per week, then I'll just set up 08:00 to 12:00 each day, rather than say 10-12:00 and then 13:00-15:00.  Keeping the start time @ 08:00 keeps the Gantt chart formatting nice :)


    Ben Howard [MVP] | web | blog | book | P2O

    Tuesday, September 15, 2015 7:10 AM
    Moderator