  • Hi,

    does anybody have any clue about what permissions a user need in order to be able to convert an Idea in a Sharepoint List to a project in PS2013?

    It works with an Admin, but not with a user configured as a PM.

    Thanks,

    Fabrizio.

    Friday, August 30, 2013 8:07 AM

All replies

  • Hi Fabrizio,

    Following article clearly talks about how to convert the SharePoint task list to a project and even talks about permissions:

    http://technet.microsoft.com/en-us/library/jj679950%28v=office.15%29.aspx

    Let me know if you are looking for more specific answer here.


    Vikram Daruru - MSFT

    Tuesday, January 13, 2015 7:01 AM
    Moderator
  • i believe it should have create project permission in PWA.


    Nur Mondal

    Tuesday, January 13, 2015 11:28 AM
  • Hi Fabrizio,

    I guess the following global permissions are required:

    • Log on
    • Contribute to Project Web App
    • New project


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |