MS Project 2016 Summary Task Value Calculation Problem In Grouping View RRS feed

  • Question

  • Hello,

    In MS Project 2016, we create a new column and formula for calculating physical complete.  (Attached view 1)

    Formula calculates values for summary tasks in Gantt Chart view however we can not calculate the values for summary tasks in grouping view.  (Attached view 2)

    Can you please help us how to see the values on yellow highlighted summary tasks in grouping view?

    Best Regards.

    ALPER

    Saturday, November 21, 2015 8:06 PM

All replies

  • alpersoy --

    Open the project in question, then click Project > Custom Fields.  In the Custom Fields dialog, select the field containing the formula.  In the Calculation for Task and Group Summary Rows section of the dialog, you need to have the Use Formula option selected.  Do you have it selected?  Please let us know and we will try to help you.


    Dale A. Howard [MVP]

    Saturday, November 21, 2015 11:38 PM
    Moderator
  • Hello Dale,

    I have also tried them all, but it does not work,

    Do you have any other solution?

    If possible I can send you the file...

    Best regards.

    ALPER 

    Monday, November 23, 2015 6:50 AM