changing between edays and regular working days RRS feed

  • Question

  • I can't figure out how to switch lag time durations from edays back to regular work days. I have a large Project schedule where everything, including lags, was entered in regular work days. However now anytime I enter a lag duration it automatically appears in edays. I must have somehow "turned on" edays (although I don't remember how I did that). Now I just want to turn off edays and have everything appear in days. How do I make this change? All task durations are in "days" it's just the lag durations that I'm having trouble with.

    Thanks for your help!

    Wednesday, September 28, 2016 6:15 PM

All replies