Calculating dates problem... RRS feed

  • Question

  • Hi

    I created a date field called Planned Finish date.  The problem is that that the date is stored with an 8 am extension and the Finish date is a 5pm extension.  When I use the DateDifferent function it returns the project is late even if both dates are on the same day.  Is there anything I can do about this?  

    Many thanks 

    James 

     




    • Edited by JamesP435 Wednesday, June 14, 2017 1:56 PM
    Wednesday, June 14, 2017 1:56 PM

Answers

  • Use either DateValue or Int function to remove the time part. For example, perform the comparison for equality as follows:

    DateValue([Planned Finish]) = DateValue([Finish]) or Int([Planned Finish]) = Int([Finish])

    Both expressions compare only the date parts of the date information by ignoring the time parts.


    Ismet Kocaman | eBook on Formulas


    • Edited by Ismet Kocaman Wednesday, June 14, 2017 10:48 PM
    • Marked as answer by JamesP435 Thursday, June 15, 2017 6:04 AM
    Wednesday, June 14, 2017 10:45 PM

All replies

  • How are you filling the Planned Finish Date? Is it a formula or is it entered by hand?
    Wednesday, June 14, 2017 2:29 PM
  • If you are comparing the dates in their text format then you need to convert them to dates.


    Sam Hobbs
    SimpleSamples.Info

    Wednesday, June 14, 2017 5:20 PM
  • Use either DateValue or Int function to remove the time part. For example, perform the comparison for equality as follows:

    DateValue([Planned Finish]) = DateValue([Finish]) or Int([Planned Finish]) = Int([Finish])

    Both expressions compare only the date parts of the date information by ignoring the time parts.


    Ismet Kocaman | eBook on Formulas


    • Edited by Ismet Kocaman Wednesday, June 14, 2017 10:48 PM
    • Marked as answer by JamesP435 Thursday, June 15, 2017 6:04 AM
    Wednesday, June 14, 2017 10:45 PM
  • It's a date field



    • Edited by JamesP435 Thursday, June 15, 2017 1:55 AM
    Thursday, June 15, 2017 1:54 AM
  • I didn't think so Sam.  The formula is:

    IIf([Planned Project Acceptance] = ProjDateValue("NA"), "grey", IIf([Finish]>[Planned Project Acceptance], "red", "green"))




    • Edited by JamesP435 Thursday, June 15, 2017 1:57 AM
    Thursday, June 15, 2017 1:57 AM