none
Project Managers don't see the details (Schedule) of their project RRS feed

  • Question

  • Hello,

    In this company, PM don't create their projects : they are created by the PMO. Then the PMO set the PM as Owner of the projects.

    So the PM can see their projects in the Project Center, but they cannot see the project details: they cannot see the detail of the Gantt Chart.

    What did I miss?

    Thanks for your help

     

    Thursday, July 18, 2013 11:07 AM

Answers

  • Hi,

    OK, let me ask in a different way: Is PM able to see schedule after publishing? Otherwise we need to investigate deeper.

    Barbara

    • Marked as answer by WLID1966 Thursday, July 18, 2013 1:05 PM
    Thursday, July 18, 2013 11:34 AM
    Moderator

All replies

  • Hi,

    did PMO perform a publish after changing owner?

    Barbara

    Thursday, July 18, 2013 11:14 AM
    Moderator
  • Hi Barbara,

    No, the PMO did not publish the project but don't worry: That works better when the PMO don't forget to Check in the project!

    Thanks

    Thursday, July 18, 2013 11:29 AM
  • Hi,

    OK, let me ask in a different way: Is PM able to see schedule after publishing? Otherwise we need to investigate deeper.

    Barbara

    • Marked as answer by WLID1966 Thursday, July 18, 2013 1:05 PM
    Thursday, July 18, 2013 11:34 AM
    Moderator
  • Yes, the PM is able to see Schedule after publishing.

    Thursday, July 18, 2013 12:20 PM
  • That's fine. Thanks for confirmation.

    Regards
    Barbara

    Thursday, July 18, 2013 12:32 PM
    Moderator