  • Hi,

    i have already enable Allow projects to use local base calendars settings.

    when PM upload project with local calendar getting message

    "Enterprise Standard Calendars are needed" message displays when i save an old project plan from Project Professional to Project Online.


    Pls guide why this setting are not impacting.

    thx
    Thx


    iffi

    Friday, July 6, 2018 12:21 PM

All replies

  • Hi,

    please ask your PM to rename his local calendar to something different. Using the default name will force the system to replace the local calendar by Enterprise calendar.

    Regards
    Barbara

    Tuesday, July 10, 2018 7:16 AM
    Moderator
  • Hi,

    local calendar name already different from enterprise. at enterprise we have standard and ABC calendar where local has different name like mycalendar.

    pls guide.

    thx


    iffi

    Tuesday, July 10, 2018 7:46 AM
  • Hi,

    I am sorry for late response and not thinking before my first reply. This message will always show up. It will not affect your schedule, if you are not using any calendar in your project with the same name as an Enterprise calendar (Resource, Task or Project Calendar). This message just tells you, that you have some additional calendars you can use.

    Regards
    Barbara

    Saturday, July 14, 2018 10:35 AM