Project Server 2013: Enterprise Calendar across all projects RRS feed

  • Question

  • Hello,

    I am looking to implement a company calender across all projects. My understanding of this so far is that you can create an enterprise calender with off days, bank holidays etc. and choose this calender when creating the project in project professional.

    Is there a way to apply this calender automatically to all projects or must it be done manually for each project?

    Thanks,

    Aaron.

    Wednesday, June 3, 2015 11:03 AM

All replies

  • Aaron --

    By default, the enterprise Standard calendar is applied automatically as the Project Calendar for every new project.  Because of this, you can easily meet your requirement by adding company holidays to the enterprise Standard calendar.  This will immediately impact the schedule of every project in your Project Server instance, which is the behavior you would want.  Hope this helps.


    Dale A. Howard [MVP]