Is there Task Create Time in PWA (server 2010) RRS feed

  • Question

  • I know there is "task crate date/time" field in project 2010,but can't find anything alike in PWA.

    Is there anyone like this field to mark that time/date ?

    Thursday, August 29, 2013 4:38 AM

All replies

  • Hi Alex --

    If you are referring to the built-in 'Created' task field in MS Project 2010 that displays the date and time when a task was added to the project schedule, then yes, this field also exists in Project Server 2010. It is also called the 'Created' field.

    If you want to see the 'Created' task field in a PWA project view, then you need to ask your Project Server administrator to add it to a view so that you can see it.

    Good luck!

    -- tz


    Tony Zink | Vice President, EPMA | http://www.epmainc.com | Blog: http://www.epmablog.com | Training: http://www.epmainstitute.com

    Thursday, August 29, 2013 5:16 PM
  • I found that field,but the date in this field can't bring into PROJECT2010 . The date in Project 2010 is ok to see in PWA. Is there sth wrong in PWA?