resource custom field RRS feed

  • Question

  • Hi,

    How to create a custom field for resource availability using formula in PWA and display it in the resource centre?

    Thanks!

    Friday, March 2, 2018 6:32 AM

Answers

  • Roshni -

    Capacity is calculated as the Max. Units for the resource, multiplied by the number of hours on the resource's calendar.  For example, for most resources their Max. Units is 100% and their work schedule is 8 hours per day, so their Capacity would be 8 hours/day, 40 hours/week, etc.  If a resource's Max. Units was only 75% and their work schedule was 8 hours per day, their Capacity would be 6 hours/day, 30 hours/week, etc.

    Keep in mind that the system also deducts nonworking time from the Capacity for a resource.  This nonworking time usually comes in two forms:  company holidays and vacation time.  So, if a resource would normally have a Capacity of 40 hours/week, but there is a company holiday during one week, the Capacity for that week would only be 32 hours.

    Make sense?  Hope this helps.


    Dale A. Howard [MVP]

    Monday, March 12, 2018 9:16 PM
    Moderator

All replies

  • Roshni --

    The Availability field is calculated by Project Online for every resource PER TIME PERIOD using the following formula:

    Availability = Capacity - Work

    So, for example, if the Capacity for a resource is 40 hours each week, and the resource is assigned to 32 hours of project work during a week, the Availability for the resource for that week would be 8 hours.  The Availability for a resource will vary over time, depending on how much project work the resource is assigned each week.

    Given the above information, I do not believe it would be possible to create a single formula for use in the Resource Center page to display the resource's availability for project work.  You would be better off creating a report for this purpose, such as in Power BI for example.  Hope this helps.


    Dale A. Howard [MVP]

    Friday, March 2, 2018 2:35 PM
    Moderator
  • Hi Dale,

    Thanks for the reply.

    The capacity here is in terms of Max Units right?

    Thanks,

    Roshni


    Monday, March 12, 2018 12:46 PM
  • Roshni -

    Capacity is calculated as the Max. Units for the resource, multiplied by the number of hours on the resource's calendar.  For example, for most resources their Max. Units is 100% and their work schedule is 8 hours per day, so their Capacity would be 8 hours/day, 40 hours/week, etc.  If a resource's Max. Units was only 75% and their work schedule was 8 hours per day, their Capacity would be 6 hours/day, 30 hours/week, etc.

    Keep in mind that the system also deducts nonworking time from the Capacity for a resource.  This nonworking time usually comes in two forms:  company holidays and vacation time.  So, if a resource would normally have a Capacity of 40 hours/week, but there is a company holiday during one week, the Capacity for that week would only be 32 hours.

    Make sense?  Hope this helps.


    Dale A. Howard [MVP]

    Monday, March 12, 2018 9:16 PM
    Moderator
  • Thanks Dale!!!
    Monday, March 19, 2018 10:54 AM