Project Workspace Auto permissions provisioning RRS feed

  • Question

  • Have Project Server 2010 in a SharePoint 2010 farm. 

    Have custom EPT with custom site template.

    Have custom groups with custom permissions and custom categories assigned.

    Want to have permissions assigned to the new Project Workspaces when they are provisioned according to the custom groups. 

    Cannot figure out where to set what groups are assigned to the new project workspaces. 

    Where is this setting? 

    Thanks.


    Kevin Hughes Solutions Architect MCT, MCITP, MCSA, MCDBA, MCSA, Net+, A+, ITIL

    Wednesday, April 24, 2013 4:10 AM

All replies

  • Hi Kevin,

    project workspace permission are based on Users's role, and permissions allowed as per group settings to user,  in project as follows:

    • Project managers: who have published a project or who have Save Project permissions on a project are added to the Project Managers (Microsoft Project Server) site group.
    • Team members: with assignments in a project are added to the Team members (Microsoft Project Server) site group.

    If you have configured Project Site Permission setting, under Project Site Provisioning Settings section of server settings, as Automatically synchronize then based on above users should get an access to project site.

    http://technet.microsoft.com/en-us/library/gg982961(v=office.14).aspx

    hope this helps.


    Khurram Jamshed - MBA, PMP, MCTS, MCITP ( Blog, Twitter, Linkedin )