Overtime for Task and Resource RRS feed

  • Question

  • Hi There,

    I have a task assigned for 10 days with Resource A at 100% commitment.

    I have agreement for resource A to work 4 hours overtime each day over the 10 days on Task B

    How do I allow this over allocation to occur without project levelling and moving the tasks.

    IE. I want them stacked

    I do not want to set his calendar to 12 hour days for these 2 weeks in case dates move, and then other tasks get the 12 hour days.

    I simply want him to be able to work 4 hours overtime on Task B whenever it is scheduled. 

    Thnx

    Jeff







    • Edited by Uthall Thursday, September 22, 2016 12:12 PM
    Thursday, September 22, 2016 10:20 AM

Answers

  • Hi,

    You have to edit the resource from the resource sheet and in the general tab set his avaibility so that during the 2 weeks, it will go up to 150%, then go back to 100%. Doing this, the resource is not overallocated and it should not be leveled.

    Then if you add 1.5d after those dates, you'll see the overallocation.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Thursday, September 22, 2016 12:19 PM
    Moderator

All replies

  • Hi,

    You have to edit the resource from the resource sheet and in the general tab set his avaibility so that during the 2 weeks, it will go up to 150%, then go back to 100%. Doing this, the resource is not overallocated and it should not be leveled.

    Then if you add 1.5d after those dates, you'll see the overallocation.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Thursday, September 22, 2016 12:19 PM
    Moderator
  • Thanks Guillaume, worked perfectly......
    Sunday, October 2, 2016 3:21 PM