  • I am trying to assign a labor resource to a task, but when I try to increase its assigned units from 100%, the cost remains the same. I have set maximum units of this resource at 2000% in the resource sheet. Can anyone assist in solving this issue?
    Saturday, April 4, 2020 12:34 PM

Answers

  • Hi,

    If the task is set to "fixed work" (task type), even if you increase the units, the duration only will increase, and not the work. So the cost will remain unchanged. Tru to set the task to fixed duration and it should be ok.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Saturday, April 4, 2020 2:15 PM
    Moderator

All replies

  • Hi,

    If the task is set to "fixed work" (task type), even if you increase the units, the duration only will increase, and not the work. So the cost will remain unchanged. Tru to set the task to fixed duration and it should be ok.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Saturday, April 4, 2020 2:15 PM
    Moderator
  • This has solved the problem. Many thanks.