How to other project manager will receive timesheet hours from the team members. RRS feed

  • Question

  • Project Server 2010

    Difference b/w project owner and project manager ?

    If one first Project Manager publish his project and team members fills the timesheet against his project.

    and all timesheet hours filling by his team members are coming to that project manager profile.

    But after sometime the second Project Manager opens the project and want the team members filling timesheet hours will come to his PWA profile.

    Then what the second project projects manager need to do . that project managers timesheet hours will come to his PWA profile for approval.

    Scenario :

    If we are working on support projects . then managing the projects by first project manager. and receive the timesheet hours from team members by another PM .

    and If new tasks need to be added . then first project manager can do this . but second project manager can receive only timesheet hours from team members .

    How it can be possible ?

    Thursday, August 30, 2012 12:05 PM

All replies

  • A resource can have only one Time sheet Manager and multiple status managers.

    Open you project plan in project professional and add a column named "Status Manager". Hours entered against task's will go to the status manager for that task.

    Time sheet submitted by resource will go to the time sheet manager of that particular resource.

    If you are operating on Single Entry Mode then by default when a resource enters his/her time sheet, then time sheet will go to his/her time sheet manager and the updates for the tasks against which he/she entered time will go to the respective status managers for those tasks.


    Abhijeet M. Mohite Please Mark As Answer if my post solves your problem or Vote As Helpful if a post has been helpful for you.