Issue with Task updates RRS feed

  • Question

  • Hi All,

    Recently I am facing an issue with the Task updates. Below is the scenario:

    1. Shows 7 updates from resources on home page (Screenshot below)
    2. After going to approval page, only 2 tasks shown. Approved the 2 tasks
    3. Now shows 5 task updates from resources on the home page
    4. Clicking on Approval centre, does not show any tasks
    5. If MSP is opened, message that Team Members have submitted 5 updates to the plan. Would you like close this project and apply these updates in the plan? (Refer screen shot). Clicked on No
    6. Saved and Published the Project
    7. After this the 5 tasks were shown for approval

    Cheers, Amit Wairkar

    Monday, March 10, 2014 9:13 AM