none
Copy values from Cost to Enterprise Custom Field RRS feed

  • Question

  • I need to copy the values from Cost to a Enterprise Custom field.  I created the custome field with a formula with [Cost]. It does nothing.  I even tried for kicks to have [Cost] +1 and even just 100.  They all fail. Any ideas? Thanks!

    Monday, August 12, 2013 12:32 PM

All replies

  • Morning David,

    Just tested the custom formula you desccribed and it seems to be working for me. Screenshot below in case this is any help:

    One thing to check - is your project set to auto-calculate? Press f9 and see if the values are correct then. If f9 corrects it, then auto-calculate is switched off, and can be switched on via Tools > Options.


    • Edited by Andrew Simpson Tuesday, August 13, 2013 8:29 AM Updated screenshot
    Tuesday, August 13, 2013 8:27 AM