none
Project server 2010 RRS feed

  • Question

  • Hi,

    I am unable to view the tasks assigned to me under the timesheet.I have a number of tasks created that are manually scheduled and assigned to various resources and nobody is able to see their respective tasks under the timesheet view.Please help.

    Thanks,

    Raj

    Tuesday, June 26, 2012 6:14 PM

All replies

  • Hi ,

    Have you published the project?

    Are the resources added to the tasks committed and not proposed?

    Are enterprise resources added to the project or are the resources local?

    What happns if user try to add task manually? Are you using Single Entry mode?


    Hrishi Deshpande – Senior Consultant DeltaBahn
    Blog | < | LinkedIn

    Tuesday, June 26, 2012 6:28 PM
    Moderator
  • Hi Raj,

    Are the resources able to see the tasks on the Tasks page in PWA? Is it just the Timesheets where the tasks do not appear?

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com

    Tuesday, June 26, 2012 7:42 PM
    Moderator