Manage Resource Calendars (Project Server 2013) RRS feed

  • Question

  • Hi,

    Is it possible in Project Server 2013, to grant a project Manager the permission to manage the calendars of his resources, without giving him access to all the resource settings?

    Thanks

    Saturday, October 12, 2013 11:23 AM

Answers

  • Hi,

    changing the resource calendar is governed by the category permission Edit Enterprise Resource Data. A project manager with the privilege can edit any resource setting.

    How ever depending on what you want to achieve you can use a task calendar instead or grant the project manager access to an absence project without granting any access to the resource settings.

    Best,

    Renke 


    http://www.holert.com Project Management with MS Project - Oldenburg, Berlin, Munich/Germany

    • Marked as answer by Robert6156 Thursday, October 31, 2013 9:58 PM