Add Task in a project from Timesheet (PS 2010) RRS feed

  • Question

  • Hi,

    Is it possible to create, (like Project Server 2007) from a Timesheet a new task attached to a project? How to do that?

    Thanks

     

    Thursday, January 13, 2011 2:11 PM

Answers

  • In order to add a new task from timesheet (to an existing project), you will need to have the "Single Entry Mode" enabled.
    • Marked as answer by WLID1966 Friday, January 14, 2011 2:50 PM
    Friday, January 14, 2011 2:34 PM