none
PWA 2010 timesheet status says "Delegate" - cannot edit timesheet RRS feed

  • Question

  • I cannot edit a timesheet as a delegate. The status in the timesheet says "Waiting Approval". So I go to Manage Timesheets and the status says "Delegate" instead of "In Progress" or "Submitted". What does that mean?

    Thursday, April 21, 2011 3:49 PM

Answers

  • I am not sure of the Delegate status in your Manage Timesheets Page, but you will need to Recall the timesheet, before you can edit.

     


    Prasanna Adavi, PMP, MCTS Blog: http://msprojectideas.blogspot.com
    Thursday, April 21, 2011 4:02 PM
    Moderator

All replies

  • I am not sure of the Delegate status in your Manage Timesheets Page, but you will need to Recall the timesheet, before you can edit.

     


    Prasanna Adavi, PMP, MCTS Blog: http://msprojectideas.blogspot.com
    Thursday, April 21, 2011 4:02 PM
    Moderator
  • I cannot edit a timesheet as a delegate. The status in the timesheet says "Waiting Approval". So I go to Manage Timesheets and the status says "Delegate" instead of "In Progress" or "Submitted". What does that mean?


    Excactly the same problem here. Has anyone figured out what this is yet? Is it a know bug, or something that should be changed in the settings?
    Monday, March 12, 2012 8:47 AM
  • We are currently seeing this issue on our EPM 2010 instance. Does anyone know a cause/solution for this?
    Tuesday, April 2, 2013 11:03 AM