MS Project Start Date Not Changing on individual tasks RRS feed

  • Question

  • Hello!....I am using MS Project 2016. The project is set for "Auto Scheduled." I had to change the start date for a project that was already developed through Project --> Project Information while highlighting all the tasks. Although the change is reflected under the Project Information window, the Line 0 tasks still shows the old date and the tasks on the project do not reflect the change. Does someone have any insight on this?
    Wednesday, May 15, 2019 2:00 PM

All replies

  • Hi,

    please don't "move" a project by changing the start date in Project Information. There is a button "Move Project" on Project tab. This will move all tasks (including deadlines and constraint dates) according to the new project start date from "Move Project".

    Does that help?
    Barbara