Process for alerts and remainders from PWA in project server 2013 RRS feed

  • Question

  • i want to start the alerts and remainders service from pwa.so that Me and my resources will resources will receive alerts and remainders for each task assigned to them.Please tell me the process to do so.Like how to bulit team and then what next to do and how.so  that i receive alerts message to configured mail.please help.
    Wednesday, March 18, 2015 8:07 PM

All replies

  • Hey there Ashish,

       There are a couple of things to know about this:

     - AFAIK - this feature isn't available in Project Online

     - For on-premise Project Server 2013 you need to go to Central Administration->General APplication Settings->Manage PWA->Operational Policies->Alerts and Reminders and switch it on there.  If you can't see the setting make sure you have already configured the outgoing SMTP sever settings for your installation.

    Cheers,

       James.


    James Boman BSc. MCP:EAD -

    Thursday, March 19, 2015 12:05 AM
  • Sorry james but i had done these things .What i am trying to know is how to built team from PWA and assign task to resources. from PWA .So that alets will works .
    Thursday, March 19, 2015 1:41 PM
  • Ashish,

       It should work AFAIK - perhaps there is an email transport problem - Can you confirm that if you set an alert on a normal SharePoint list, that you get the alerts in your email?

    Cheers,

       James.


    James Boman BSc. MCP:EAD -