Whats the best way to split activities, few of them completing on-time while others delayed RRS feed

  • Question

  • Please suggest me what is the best way to deal this scenario. 

    Epic-1, Epic-2, Epic-3 and Epic-4 with identical task lists (activities) were planned to complete at same time but by deadline only 1 and 2 are ready. The sponsor has agreed to combine 1 and 2 ans call it 1.1 and accept the deliverable on time whereas now I need to create 1.2 Summary task and put new but same activities for 3 and 4 with new task entries. These activities will be same as those for 1 and 2 but will have own schedule. 

    What are the steps to move forward ? 

    Friday, June 2, 2017 5:16 PM

All replies

  • Here is one way of doing it:

    Create two new summary tasks.

    Call the first 'Completed tasks' and move epics 1 and 2 under it. Mark them all as complete.

    Call the second summary task "Incomplete tasks" and move epics 3 and 4 under it.

    Put new start dates for all the incomplete tasks in epics 3 and 4 and give them all a new deadline.