  • Hello Emil,

    I learned this from my guru , to add add this line, right click in the Gantt chart, click on Gridlines. Select Status Date on the left, select a line style and color, and click OK to close the box. The Status date will be shown when it’s entered in the Project Information box. I am sure it will help you.

    Regards,

    M.Enam Ur Rehman

    • Marked as answer by Emil Vega Wednesday, March 30, 2016 8:58 AM
    Wednesday, March 30, 2016 8:54 AM

All replies

  • Hello Emil,

    I learned this from my guru , to add add this line, right click in the Gantt chart, click on Gridlines. Select Status Date on the left, select a line style and color, and click OK to close the box. The Status date will be shown when it’s entered in the Project Information box. I am sure it will help you.

    Regards,

    M.Enam Ur Rehman

    • Marked as answer by Emil Vega Wednesday, March 30, 2016 8:58 AM
    Wednesday, March 30, 2016 8:54 AM
  • Yes Enam,

    It works ...