Team Planner filter tasks longer than 40 hours RRS feed

  • Question

  • Is there a way to add a filter to the team planner,

    That only shows tasks longer than 40 hours.

    I cannot seem to figure out how to use the filters.

    thanks

    Friday, June 23, 2017 2:48 PM

All replies

  • GregD101,

    The Team Planner view is a resource based view so task duration is not applicable. However, you can filter on the work content of resources. If each task has a single resource assigned full time then the work content will be equivalent to the duration. If multiple resources are assigned to a task then a filter for work greater than 40h will be at resource level, not at assignment level.

    Hope this helps.

    John