    So I’ve created a calendar that both my enterprise resources AND the plan is associated with. My new calendar has 7.5 hour days, starting at 8:30 -12:30 half hour lunch, 13:00-16:30. However, when i view a tasks that have been scheduled for 1 day on my Gantt chart, the Gantt still shows what I assume is the standard calendars, please see attached png.

     

    How do you get the Gantt to show the new calendar that has been assigned to my resources and my plans as previously mentioned.

     

    thanks  

     

    Tuesday, January 17, 2012 11:40 AM

Answers

  • Its ok, i worked it out. in P2010

     

    Right click the timeline in Gantt view > Timescale > Nonworking time > change calandar

    • Marked as answer by gdallas Tuesday, January 17, 2012 12:09 PM