none
visual report / resources per task RRS feed

  • Question

  • Hi,

    I am using project pro 2013. I want to export as a pivottable in excel the time spend by each work resource for each task (or group of tasks). I do not find how to do that. Thanks for helping.


    Misange - www.excelabo.net


    • Edited by Misange Friday, January 11, 2013 4:05 PM
    Friday, January 11, 2013 4:03 PM

Answers

  • Are you looking for Baseline Work Report, there you have resources and tasks and can get work hrs spent by resources on each task/group of tasks. If you click on Project Tab -> Go to Reports -> Visual Report -> Baseline Work Report is available there.Please let us know if you are looking for something else.

    Sapna Shukla

    • Marked as answer by Misange Friday, January 11, 2013 4:51 PM
    Friday, January 11, 2013 4:41 PM
    Moderator

All replies

  • Are you looking for Baseline Work Report, there you have resources and tasks and can get work hrs spent by resources on each task/group of tasks. If you click on Project Tab -> Go to Reports -> Visual Report -> Baseline Work Report is available there.Please let us know if you are looking for something else.

    Sapna Shukla

    • Marked as answer by Misange Friday, January 11, 2013 4:51 PM
    Friday, January 11, 2013 4:41 PM
    Moderator
  • YESS ! I am not familiar with this vocabulary yet (especially in english...)

    Thanks, it saves a lot of time :)


    Misange - www.excelabo.net

    Friday, January 11, 2013 4:51 PM
  • You are most welcome Misange :)

    Sapna Shukla

    Friday, January 11, 2013 5:00 PM
    Moderator