Problems with resource loaded schedule and the resource sheet syncing RRS feed

  • Question

  • I have a resource loaded schedule and I changed the resource sheet on the resources (i.e. - I changed their availability from 100% to another percentage). How can I get the schedule to update the tasks when I change the information on the resource sheet? The tasks that they have already been assigned to are still being calculated as if they are 100%. Please help!
    Friday, February 15, 2013 4:27 PM