Actual Work divided between Local and Enterprise Resource RRS feed

  • Question

  • Hello all,

    While importing our project files using the Import Wizard, we are having instances of part of the resources on our tasks not syncing to the enterprise.  When the mapping resources options comes up, the resources from our import is able to connect to the Enterprise Pool (because the names are identical); however, once we press OK, the system still creates a local resource and divides the actual hours imported between the local and enterprise resource.

    This is an issue for us, because we have about 76 projects to import and all of our enterprise resources have the historical rate information manually entered.  When these local resources are generated, it makes a separate local resource for each instance on each project being worked by that person.  This would mean that for every project, we would have to manually update the historical rate information for every local resource occurrence.

    While we are wiling to do it that way if necessary, we would like to see if there is a fix.  Any thoughts on how to merge the resources together or at least find a way to have the rate information display across both the local and enterprise resource? 

    Thanks in advance for your help!

    Tuesday, July 5, 2016 2:30 PM