none
Timesheet Administrative Line Disappearance RRS feed

  • Question

  • We have a resource who, for this Timesheet Period, has had her Administrative Lines (Administrative, Time Away, etc.) somehow disappear.  Has anyone else encountered this?  Is there a way to bring them back?  There are no filters, groups or special views that are in use to cause this so it's especially weird (to me anyways).

    Any and all help would be most welcome, thank you!!

    Tuesday, June 21, 2016 7:52 PM

Answers

  • Hi UTDZ,

    Are you able to see the Administrative task under Timesheet >> Add Row >> Add Non Project Line Item from the resource timesheet page.


    -SNKBalaji

    • Marked as answer by UTDZ Wednesday, June 22, 2016 1:30 PM
    Wednesday, June 22, 2016 6:54 AM

All replies

  • Hi UTDZ,

    Are you able to see the Administrative task under Timesheet >> Add Row >> Add Non Project Line Item from the resource timesheet page.


    -SNKBalaji

    • Marked as answer by UTDZ Wednesday, June 22, 2016 1:30 PM
    Wednesday, June 22, 2016 6:54 AM
  • Thank you for the reply!

    Yes, rather sheepishly saw that a couple hours after I had posted....haha.  Oh well.

    Thank you very much again!

    Wednesday, June 22, 2016 1:29 PM
  • Hi UTDZ,

    Happy to here it is working, Thank you for the confirmation :)


    -SNKBalaji

    Thursday, June 23, 2016 4:38 AM