  • Hi,

    Could you give me some suggestions to build an OData report with the day by day workload of every resources on every projects, like this example :

    Day 1 Day 2      Day 3    Day 4 Day 5 Day 6 Day 31
    Resource 1 8 h 8 h 8 h 8 h 8 h 8 h 8 h 8 h
    Resource 2 8 h 7 h 7 h 7 h 7 h 7 h 7 h 8 h
    Resource 3 8 h 6 h 6 h 6 h 6 h 6 h 6 h 7 h
    Resource 4 8 h 5 h 5 h 5 h 5 h 5 h 5 h 6 h
    Resource 5 8 h 8 h 8 h 8 h 8 h 8 h 8 h 8 h
    Resource 6 8 h 9 h 9 h 9 h 9 h 9 h 9 h 8 h
    Resource 7 8 h 10 h 10 h 10 h 10 h 10 h 10 h 8 h
    Resource 8 8 h 8 h 8 h 8 h 8 h 8 h 8 h 8 h
    Resource 9 8 h 7 h 7 h 7 h 7 h 7 h 7 h 8 h
    Resource 10 8 h 6 h 6 h 6 h 6 h 6 h 6 h 7 h