The timesheet has been rejected because it contained at least one task that has been deleted or reassigned. RRS feed

  • Question

  • Hi,

    We are working on Project Server 2010 SP2.

    After complete approval of a timesheet and their lines, the timesheet of the user change from "Approved" to "The timesheet has been rejected because it contained at least one task that has been deleted or reassigned"

    The root cause seems to be linked to a rename of tasks. Other people on the same tasks are not impacted.

    This problem appeared on other projects and other resources (random).

    Any help is welcome ...

    Thanks,

    Christophe.

    Friday, November 29, 2013 4:18 PM

All replies

  • Hi

    renaming of tasks should not be a problem. A problem could be moving a task using cut&paste (what is a copy and delete), because task and assignment(s) get new UIDs and the timesheet line is linked to that UID.

    Regards

    Christoph


    Christoph Muelder | Senior Consultant, MCSE, MCT | SOLVIN information management GmbH, Germany

    Monday, December 2, 2013 10:25 AM