Project Server 2010
I have a project with many tasks that run constantly, so I set a 24/7 project calendar. Most are calculating correctly, but one of those task with a Fixed Duration of 10 days is reflecting only four calendar days (i.e. 8/15 - 8/19). The
generic resource has the same 24/7 calendar with 100% unit allocation.
Settings:
Autoscheduled, As soon as possible, no dates constraints and only one FS predecessor.
Same result regardless if the "ignore resource calendar" or "effort based" are selected.
Testing with fixed work of 240 hours generates 24 day duration but the correct 8/15 - 8/25 dates.
What am I overlooking!?
(Oddly, on another task with same resource and settings, a 64.5 day duration task is calculating 26 days and on one with 36 day duration, 45 days.)
Thanks in advance!