How to user enter more than 8 hours into single task of one day. RRS feed

  • Question

  • If the user has one task assigned in monday of 8 hours .

    Company using Single Entry Mode.

    In timesheet there is showing 8 planned hours.

    but if user enter 10 hour or 2222 hour in that task actual hour. it is accepted and calculating at bottom of total.

    what is this ?

    because in project server 2007 . it will stop the user with the dialog box. that it is not allowed to enter more than 8 hours a day in a single task or multiple task.

    Wednesday, August 22, 2012 8:22 AM

Answers

  • Hi John,

    Max hours per day for the timesheets can be set on the Timesheet Settings and Defaults page in Server settings. This will not stop users entering more than X amount of hours on the grid, but they will not be able to save the timesheet until they have corrected the hours.

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com

    • Marked as answer by John.Eddie Wednesday, August 22, 2012 9:28 AM