Hello,
I have multiple DPM servers, one main DPM server backup remote DPM servers that backup reqular servers. What should be upgraded first, main server or remote servers? Or they must be upgraded all together?
Hi Alexandro,
No interoperability exists between DPM 2010 and DPM 2012 (http://social.technet.microsoft.com/Forums/en-US/dataprotectionmanager/thread/cc790b34-7244-47e9-9812-0248b39cd4ad#62a9a1f2-f7a6-4f75-b084-d84b53f7292c). You will need to upgrade
them all.
Here is a good post on upgrading DPM 2010 to DPM 2012 by Kevin Green of Ergo.
http://kevingreeneitblog.blogspot.com/2011/09/upgrading-system-center-dpm-2010-to-dpm.html
My Blog | www.buchatech.com | www.dpm2010.com
If you found this post helpful, please give it a "Helpful" vote. If it answered your question, remember to mark it as an "Answer". This posting is provided "AS IS" with no warranties and confers no rights! Always test ANY suggestion in a test environment