Skip to stage resetting entry and exit dates RRS feed

  • Question

  • I have a requirement where we want to measure a project time spent in a particular stage e.g. Project A was 'parked' in selection stage from X date to Y date. We calculate difference of entry (X date) and exit (Y date) in stage table to get this information - this works great, unless we use skip to stage feature which resets entry and exit date to the date this feature was executed.

    Is there any way I can keep the old dates and not let the skip to stage feature reset them?

    Wednesday, May 25, 2011 11:00 AM

Answers

All replies