Creating customized report in MS Project Professional 2010 RRS feed

  • Question

  • I am new to customizing reports and I am attempting to create a customized report in MS Project Professional 2010 that would show me all tasks that are greater than 5 business days late.  I thought that I could perhaps create a filter that would select those tasks where the finish variance was greater than 5 days?  I believe the finish variance is a text field so would I have to move the variance to a number field first so I could do this?  Is there a easier way to do this which I am overlooking?  Any help pointing me in the right direction is greatly appreciated. Thx.
    Tuesday, October 4, 2011 8:06 PM

Answers

  • blawson1999,

    The Finish Variance field is a duration field, not a text field. The filter you want should be as simple as,

    And/Or Field Name Test Value

    Finish Variance is greater than 5d

     

    Hope this helps.

    John

    • Marked as answer by blawson1999 Thursday, October 6, 2011 12:53 PM
    Tuesday, October 4, 2011 8:51 PM

All replies

  • blawson1999,

    The Finish Variance field is a duration field, not a text field. The filter you want should be as simple as,

    And/Or Field Name Test Value

    Finish Variance is greater than 5d

     

    Hope this helps.

    John

    • Marked as answer by blawson1999 Thursday, October 6, 2011 12:53 PM
    Tuesday, October 4, 2011 8:51 PM
  • John,

    Tried it and it worked like a charm.  Thanks again!!!!

    Thursday, October 6, 2011 12:53 PM
  • blawson1999,

    You're welcome and thanks for the feedback.

    John