Transpose the summary tasks with the subtasks RRS feed

  • Question

  • Hi!

    I have a programme of a hospital construction. I Set the WBS my summary tasks are works, than i set the Blocks and Floors. I can See all works' percentage by block basis. 

    I want to see the completion of Blocks for all works.

    My existing Schedule is this : 

    And i want to see also like this : 

    Thanks!