week time schedule in MS Project 2010 RRS feed

  • Question

  • How to set the week time schedule to start numbering week 1 in january,

    (currently using 3 tiers, year, month, week), w week; 1...52, 1..

    now the numbering start at 1 in August ???

    Friday, April 26, 2013 10:11 AM

All replies

  • Hi ThomasSwedPower,

    Right click on the timescale in the Gantt chart and choose Timescale from the shortcut menu.  Remove the check from the box "Use Fiscal year".

    I hope this helps.

    Julie

    Friday, April 26, 2013 11:26 AM
    Moderator