  • Hi,

    for Earned Value fields you need to save a baseline and then update the progress.

    Hope this helps,

    Renke


    http://www.holert.com Project Management with MS Project - Oldenburg, Berlin, Munich/Germany

    Monday, February 4, 2013 9:00 PM
  • Also take care that if you are using status date your EVA calculation are based on that date and not current date.  I would advise that you use status date and update each time you track your project.  The reason being if you use current date and track you plan today, you will get current CPI and SPI but tomorrow the date has moved on and your SPI and CPI will appear to be lower than expected.
    Thursday, April 11, 2013 10:39 AM