    I know how the Status Manager (=Approval Manager) functionality is supposed to work in PS2010, however in my case it doesn't work correctly.

    Steps (I am an EPM administrator)

    1. Open a Project schedule in MS Project Profesional 2010

    2. Add column Status Manager

    3. Set myself as the Status Manager for an existing task. I Also added myself as a project team member to this project.

    4. Publish the project, wait until the publish is completely finished (I checked the queue)

    5. Open my timesheet.

    6. Add myself to a Task in the project, for which I am the Status Manager

    7. When I click on the Task details I still see the original Status Manager for this task as Approval Manager and not my name!

    Further information, this is a EPM environment that I migrated from 2003 to 2010, using 2007VME.

    Looking forward to your suggestions.


    Marcel Visscher QS solutions

    Wednesday, June 27, 2012 10:33 AM

All replies

  • Hello all,

    I found that the following steps will work correctly.

    Steps (I am an EPM administrator)

    1. Open a Project schedule in MS Project Profesional 2010

    2. Add column Status Manager

    3. Set myself as the Status Manager for an existing task. I Also added myself as a project team member to this project.

    EXTRA: assign myself to that task in the project schedule!

    4. Publish the project, wait until the publish is completely finished (I checked the queue)

    5. Open my timesheet.

    7. When I click on that Task details I see my name as the Status Manager, this is correct.

    Sounds like a bug to me.....

    Looking forward to your suggestions.


    Marcel Visscher QS solutions