Critical path is not displayed RRS feed

  • Question

  • I made the schedule of my project, but when I ask to show the critical path, it is not displayed - Even I marked "critical path" in "format". What can it be?

    Thank you

    Thursday, July 21, 2016 7:45 PM

All replies

  • Davi,

    It could be many things. You do not give us enough information, so let's find out more about what you have.

    First, what version of Project are you using? Is it updated with the latest Cumulative Update? The easiest way to do that is to run Windows Update.

    Second, are your task linked in a logical sequence with no constraints?

    Third, when you display the Total Slack field, are there any tasks with "0 days"? If so, how many?

    Fourth, are you in a Project Server environment?

    Fifth, are your tasks manually scheduled or auto-scheduled?

    Sixth, did you modify the default Gantt Bar styles?

    John

    Thursday, July 21, 2016 7:57 PM