Duration of the task is displayed as fractions. RRS feed

All replies

  • Hi,

    Make sure there is consistency between the working time per day as shown in the calendar (through Change Workingtime, I don't know how that is in Russian) versus the definition of "Hours per day" as set in File, Options, schedule.

    Greetings,

    Thursday, July 4, 2013 2:10 PM
    Moderator
  • You have task calendars applied to pretty much all tasks.  My guess is that the schedule was not doing what you wanted it to do so you are over-riding the project calendar with a task calendar that, as Jan notes, does not match the definition of day and week set in Options.
    Thursday, July 4, 2013 2:35 PM
    Moderator