  • I work in a company where each developer works in several projects at a time. They register their hours in PWA, and it would be easy for them if they could view only those Projects in which they are currently working and not the projects that are already finished. Is there a way to do this?

    Thanks in advance

    Regards,

    Margarita.-

    Wednesday, November 2, 2011 6:10 PM

Answers

  • Margarita --

    If your organization is using Project Server 2010, I would strongly recommend you teach your PMs how to use the Close Tasks to Update feature. When a project is completed, the PM can use this feature to remove all tasks from completed projects from each team member's Timesheet page and Tasks page in PWA.  Hope this helps.