Project WOrkspace migration RRS feed

  • Question

  • Hi,

    We have heard from one other EPM customer who migrate from PS2007 to PS 2010 that the Project workspace once migrated (with the technet 5 database attached procedure "Full Database Migration - Project data and PWS Site Data")

     needed to be relinked manually one by one : PS2010 properly create new web site, but cannot not retrieve former data in the new Project SharePOint web site, created when publishing the project 2007 on WSS 3.0 . As a consequence : usage of DELIVERABLES in Project Pro 2010 do no more work properly, since the SharePoint list cannot be reached.

    This customer had to redirect URL with DNS to try to recover data.

    Didier


    Didier Maignan | INTEPROJET
    Tuesday, December 14, 2010 11:05 AM

Answers