Making a weekend day a working day RRS feed

  • Question

  • I am attempting to assign a task to a weekend day but Project 2010 keeps moving it to the following Monday.
    Wednesday, December 14, 2011 4:14 PM

Answers

All replies

  • Hello Jararz,

    By default, the project calendar only has working time Monday through Friday.  If you have tasks (and resources) working Saturday or Sunday, you'll need to modify the calendar.

    Project tab > Change Working time.  Either add an exception (if it is a single day occurrence) or modify the Work Week if it is an on-going issue.

    Julie

    Wednesday, December 14, 2011 4:32 PM
    Moderator
  • Ok, let me throw more into the mix. We are running Project Server 2010 and I am using a customized calendar that has the weekend designated as working days but when i attempt to set any of those days as the task start it moves the it to the following Monday.
    Wednesday, December 14, 2011 5:31 PM
  • Do you have resources assigned?  What is their calendar definition?
    Wednesday, December 14, 2011 5:51 PM
    Moderator
  • no resources assigned.
    Wednesday, December 14, 2011 6:14 PM
  • Hi,

    "I am using" you say. How exactly? Did you assign your customized calendar as a task calendar? Is this customized calendar an Enterprise Calendar?

    Greetings,

    Wednesday, December 14, 2011 6:20 PM
    Moderator
  • sorry for not being specific. Yes it is a customized Enterprise Calendar.
    Wednesday, December 14, 2011 9:48 PM
  • Did you assign it as the task calendar?
    Wednesday, December 14, 2011 10:43 PM
    Moderator