none
rejected tasks RRS feed

  • Question

  • Team members submit tasks, PM rejects them.  Although Team members do not see the rejected tasks.

    what view are they missing?  

    Thursday, February 14, 2013 1:58 PM

Answers

  • Which version of Project Server are you using?

    In 2010, rejected inputs should show up in the My Tasks view in PWA with notification in the Processing Status column. If there is some filter being applied in this view, it's possible the rows would not show.

    Graham

    • Marked as answer by Chanda Norton Thursday, December 4, 2014 4:58 PM
    Thursday, February 14, 2013 3:20 PM