none
"Update my tasks page" is empty for all users except the admins RRS feed

  • Question

  • Hi, and thank you for reading.

    This is probably a newbie question, but I have not been able to resolve this myself.

    I would like our resources to log in to the PWA and provide their updates per task. Sadly, when they go to the “Tasks” page, it is blank. Is this even the correct page? J

    Thank you in advance.

    George
    Monday, August 6, 2018 1:44 PM

Answers

  • Hi George, 

    If the resources are set up in PWA as users with Team Member access, and you add those resources to the project schedule and you publish the project schedule those resources should be able to see their tasks and provide updates per task.


    JH Blake

    Monday, August 6, 2018 2:37 PM