Closed and archived projects are still showing up in resource assigmnents in PWA 2010 RRS feed

  • Question

  • hi

    I have changed project status to completed and set it's task to NOT published ,Closed tasks status to update and Published it. 

    Project still shows up in Resource availability view for a resource....... Does anyone know why? Or do I have to make remaining work 0 to remove it from Resource assignments.

    Tuesday, December 23, 2014 5:11 PM

All replies

  • Hi Project help,

    Setting the publish column value to "no" should remove the assignment from the resource availability. See this excellent blog post. I'd advice to double check and publish again the project.

    That being said, I always recommend to set to 0 the remaining work as well.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, December 24, 2014 3:17 AM